Facilities Manual
RD3.3: Inspector's Daily Report
(see FM5:12.2)
| INSPECTOR'S DAILY REPORT (Facility) | |||
| PROJECT TITLE______________ PROJECT NO.________________ REPORT NO._______________ CONTRACT NO. _______________ |
|||
| Date ___________________________
Day: S M T W Th F S Weather: Clear___ Overcast___ Rain___ |
|||
| CONTRACTOR'S LABOR FORCE
Supervision____ Administrative_____ Skilled and Unskilled_____ Other______ Total______ |
|||
| SUBCONTRACTOR'S LABOR FORCE | |||
| SUBCONTRACTOR ___________________ ___________________ ___________________ |
NO. _____ _____ _____ |
SUBCONTRACTOR ___________________ ___________________ ___________________ |
NO. _____ _____ _____ |
| WORK PERFORMED | |||
| REMARKS | |||
| PHONE CALLS | |||
| VISITORS | |||
| ORAL INSTRUCTIONS | |||
| INSPECTOR'S SIGNATURE
_____________________________________ |
|||