New UCOP Office Building Update as of October 8, 1997

This is to provide you with an update on the new UCOP headquarters building in downtown Oakland. Information provided below updates that provided in the last bulletin, distributed on July 21, 1997.

OVERALL PROJECT PROGRESS AND SCHEDULE

The project continues to proceed well. The exterior panels of the building will be erected by the end of the month. During the next two months the panels will be aligned, welded and sealed. Exterior glass installation will be started at the end of the month and continue into January. Roofing installation is scheduled to be completed in early November.

Workstation furniture is being ordered for delivery beginning in February. Responses to an RFP for a new phone system are due in the middle of this month with a decision on a new phone system to be made by the end of November.

The project continues to be scheduled for completion on April 23, 1998, with the first move in to occur the weekend of April 25/26.


DECISION ON LEASED SPACE

At the end of last week the Regents approved execution of a lease with the Kaiser Center to house the majority of those not moving into the new building. The recommendation to sign a new lease with the Kaiser Center followed a search for the most cost effective space and a long series of negotiations with a number of suitable sites. The University will be leasing half of the third floor (to house the Computer Center and networking and computer operations staff), the entire fourth, fifth and seventh floors and half of the sixth floor. The seventh floor will be leased in its entirety rather than the sixth floor because its current build out is more suitable to the needs of the units staying in the building. Over the next few months, we will be working with the affected departments and the architectural firm of Gordon Chong and Partners to identify the specific locations of those to be housed in the Kaiser Center.


ADDITIONAL QUESTIONS?

If you have questions which have not been answered in this bulletin, please send e-mail to:  building@ucop.edu