Project Start Date: Mon 2/2/04
Project Finish Date: Mon 11/8/04
| ID | Description | % Complete | Start | Finish | Predecessors | People |
|---|---|---|---|---|---|---|
| 1 | Project Start | 100% | Mon 2/2/04 | Mon 2/2/04 | ||
| 2 | Identify group members | 100% | Mon 2/2/04 | Tue 2/10/04 | 1 | Walker,Harel |
| 3 | First group meeting | 100% | Mon 3/8/04 | Mon 3/8/04 | 2 | All |
| 4 | Distribute meeting notes | 100% | Tue 3/9/04 | Wed 3/17/04 | 3 | Walker |
| 5 | Schedule conference call | 100% | Thu 3/18/04 | Fri 3/26/04 | 4 | Walker |
| 6 | Conference call #1 | 100% | Thu 4/8/04 | Thu 4/8/04 | 5 | All |
| 7 | Distribute plan to ITLC | 100% | Thu 4/8/04 | Wed 4/14/04 | 6 | Walker,Harel |
| 8 | Sub-project plans to DW | 100% | Thu 4/8/04 | Tue 4/13/04 | 6 | All |
| 9 | Draft project schedule | 100% | Thu 4/8/04 | Wed 4/14/04 | 6 | Walker,Harel |
| 10 | Conference call - review schedule | 100% | Wed 4/21/04 | Wed 4/21/04 | 9,8 | All |
| 11 | Distribute schedule to ITLC | 100% | Thu 4/22/04 | Fri 4/23/04 | 10 | Walker,Harel |
| 12 | ITLC approval to proceed | 100% | Mon 4/26/04 | Mon 4/26/04 | 11 | ITLC |
| 13 | UCFY / YBO | 0% | Tue 4/27/04 | Mon 8/9/04 | 12 | |
| 14 | Configure Shibboleth Apache module | 0% | Tue 4/27/04 | Mon 5/10/04 | Kini | |
| 15 | Implement Shib/Apache instance of JAAS | 0% | Tue 5/11/04 | Mon 6/28/04 | 14 | Kini |
| 16 | Integrate JAAS into UCFY | 0% | Tue 4/27/04 | Mon 6/28/04 | Barman | |
| 17 | Initial integration testing | 0% | Tue 6/29/04 | Mon 7/5/04 | 15,16 | Kini,Barman |
| 18 | Integration testing w/ campuses | 0% | Tue 7/6/04 | Mon 8/9/04 | 17 | Kini,Barman |
| 19 | Develop user documentation | 0% | Tue 7/6/04 | Mon 7/26/04 | 17 | Barman |
| 20 | Train support personnel | 0% | Tue 7/27/04 | Mon 8/2/04 | 19 | Barman |
| 21 | Move to production environment | 0% | Tue 8/3/04 | Mon 8/9/04 | 38,51 | Barman |
| 22 | CDL-licensed resources | 0% | Tue 4/27/04 | Tue 4/27/04 | 12 | |
| 23 | TBD | 0% | Tue 4/27/04 | Tue 4/27/04 | ||
| 24 | Policy | 67% | Mon 4/26/04 | Mon 5/31/04 | 12 | |
| 25 | Decision to reverify ID in UCFY (pilot) | 100% | Mon 4/26/04 | Mon 4/26/04 | Baptista,James,Wilcox,Craig,Walker | |
| 26 | Develop campus policy questionnaire | 100% | Mon 4/26/04 | Mon 4/26/04 | Craig,Wasley | |
| 27 | Campuses respond to questionnaire | 67% | Tue 4/27/04 | Mon 5/31/04 | ||
| 28 | UCI | 0% | Tue 4/27/04 | Mon 5/31/04 | Roode,Arseniev | |
| 29 | UCLA | 100% | Tue 4/27/04 | Mon 5/31/04 | Wu | |
| 30 | UCSD | 100% | Tue 4/27/04 | Mon 5/31/04 | Lawrence | |
| 31 | Presentation to COVCA | 100% | Thu 5/27/04 | Thu 5/27/04 | ||
| 32 | UCSD | 5% | Tue 4/27/04 | Mon 8/16/04 | 12 | |
| 33 | Install core Shibboleth Origin | 100% | Tue 4/27/04 | Tue 4/27/04 | Lawrence | |
| 34 | Wrap Shibboleth w/ UCSD authN | 100% | Wed 4/28/04 | Wed 4/28/04 | 33 | Lawrence |
| 35 | Bridge Shib attribute service to UCSD | 100% | Thu 4/29/04 | Thu 4/29/04 | 34 | Lawrence |
| 36 | Join InCommon and InQueue | 0% | Fri 4/30/04 | Thu 5/6/04 | 35 | Lawrence |
| 37 | Config Shib for InCommon/InQueue | 0% | Fri 5/7/04 | Thu 5/13/04 | 36 | Lawrence |
| 38 | Integration testing | 0% | Tue 7/6/04 | Mon 8/2/04 | 37,17 | Lawrence |
| 39 | Move origin to production environment | 0% | Tue 8/3/04 | Mon 8/9/04 | 38 | Lawrence |
| 40 | Develop training materials | 0% | Tue 7/13/04 | Mon 8/9/04 | 38FF+1 wk | Lawrence |
| 41 | Config Blink for Shibb'ed UCFY/YBO | 0% | Tue 8/10/04 | Mon 8/16/04 | 39,40,13 | Lawrence |
| 42 | UCI | 44% | Mon 4/26/04 | Mon 8/16/04 | 12 | |
| 43 | Install dedicated server to host Shibboleth Origin | 100% | Tue 4/27/04 | Tue 4/27/04 | Roode,Arseniev | |
| 44 | Install Apache, Tomcat Java server, Sun J2SE JDK, etc. | 100% | Wed 4/28/04 | Wed 4/28/04 | 43 | Roode,Arseniev |
| 45 | Install Shibboleth v1.1 | 100% | Thu 4/29/04 | Thu 4/29/04 | 44 | Roode,Arseniev |
| 46 | Obtain web server certificate from HEPKI | 100% | Fri 4/30/04 | Fri 4/30/04 | 45 | Roode,Arseniev |
| 47 | Join the InQueue federation | 100% | Mon 5/3/04 | Mon 5/3/04 | 46 | Roode,Arseniev |
| 48 | Configure Shibboleth Origin | 100% | Tue 5/4/04 | Mon 5/10/04 | 47 | Roode,Arseniev |
| 49 | Set up OpenLDAP database using eduPerson schema | 100% | Tue 5/11/04 | Mon 6/14/04 | 48 | Roode,Arseniev |
| 50 | Test with InQueue | 100% | Tue 6/15/04 | Mon 6/21/04 | 49 | Roode,Arseniev |
| 51 | Integration testing | 0% | Tue 7/6/04 | Mon 8/2/04 | 50,17 | Roode,Arseniev |
| 52 | Move to production environment | 0% | Tue 8/3/04 | Mon 8/9/04 | 51 | Roode,Arseniev |
| 53 | Develop training materials | 0% | Tue 7/13/04 | Mon 8/9/04 | 51FF+1 wk | Roode,Arseniev |
| 54 | Create Shibbolized links to YCFY/YBO from UCI SNAP Portal | 0% | Tue 8/10/04 | Mon 8/16/04 | 52,53,13 | Roode,Arseniev |
| 55 | Join the InCommon federation when ready | 0% | Mon 4/26/04 | Mon 4/26/04 | Roode,Arseniev | |
| 56 | UCLA | 2% | Mon 4/26/04 | Mon 8/16/04 | 12 | |
| 57 | Install Test Shibboleth Origin in the Technology Sandbox. | 100% | Tue 4/27/04 | Tue 4/27/04 | Mahabalagiri | |
| 58 | Modify Shibboleth Handle Service to work with ISIS. | 100% | Wed 4/28/04 | Wed 4/28/04 | Mahabalagiri | |
| 59 | Create a prototype directory to provide data service to Shibboleth Attribute Authority. | 0% | Tue 4/27/04 | Mon 5/17/04 | Ma | |
| 60 | Upgrade test Shibboleth Origin to pilot-worthy status. | 0% | Wed 4/28/04 | Tue 5/18/04 | 57 | Mahabalagiri |
| 61 | Modify the prototype directory to match UC Federated Identity Management Requirements. | 0% | Tue 5/18/04 | Mon 6/7/04 | 59 | Ma |
| 62 | Upgrade prototype directory to pilot-worthy status. | 0% | Tue 5/18/04 | Mon 6/7/04 | 59 | Ma |
| 63 | Test pilot Shibboleth Origin with YBO and JSTOR. | 0% | Tue 7/6/04 | Mon 8/2/04 | 60,62,17 | Mahabalagiri,Ma |
| 64 | Develop user education materials. | 0% | Tue 7/13/04 | Mon 8/9/04 | 63FF+1 wk | Mahabalagiri,Ma |
| 65 | Develop support documentation / Train support staff. | 0% | Tue 7/13/04 | Mon 8/9/04 | 63FF+1 wk | Mahabalagiri,Ma |
| 66 | Rollout the pilot. | 0% | Tue 8/10/04 | Mon 8/16/04 | 63,64,65,13 | Mahabalagiri,Ma,Wu |
| 67 | Join InCommon. | 0% | Mon 4/26/04 | Mon 4/26/04 | Wu,Worth | |
| 68 | Service Available | 0% | Mon 8/16/04 | Mon 8/16/04 | 32,42,56,24,13,22 | |
| 69 | Evaluation | 0% | Tue 8/17/04 | Mon 11/8/04 | 68 | |
| 70 | Technology Implications | 0% | Tue 8/17/04 | Mon 10/11/04 | ||
| 71 | Support Implications | 0% | Tue 8/17/04 | Mon 10/11/04 | ||
| 72 | Organizational Implications | 0% | Tue 8/17/04 | Mon 10/11/04 | ||
| 73 | Risk Analysis | 0% | Tue 10/12/04 | Mon 10/25/04 | 70,71,72 | |
| 74 | Policy Recommendations | 0% | Tue 10/26/04 | Mon 11/8/04 | 73 | |
| 75 | Follow-On Recommendations | 0% | Tue 10/26/04 | Mon 11/8/04 | 73 |