UC Federated Authentication


Project Start Date: Mon 2/2/04
Project Finish Date: Mon 8/2/04

Groupware Phase I

ID
Description
% CompleteStartFinishPredecessorsPeople
1
Project Start
100%Mon 2/2/04Mon 2/2/04  
2
Identify group members
100%Mon 2/2/04Tue 2/10/041Walker,Harel
3
First group meeting
100%Mon 3/8/04Mon 3/8/042All
4
Distribute meeting notes
100%Tue 3/9/04Wed 3/17/043Walker
5
Schedule conference call
100%Thu 3/18/04Fri 3/26/044Walker
6
Conference call #1
100%Thu 4/8/04Thu 4/8/045All
7
Distribute plan to ITLC
100%Thu 4/8/04Wed 4/14/046Walker,Harel
8
Sub-project plans to DW
100%Thu 4/8/04Tue 4/13/046All
9
Draft project schedule
100%Thu 4/8/04Wed 4/14/046Walker,Harel
10
Conference call - review schedule
100%Wed 4/21/04Wed 4/21/049,8All
11
Distribute schedule to ITLC
100%Thu 4/22/04Fri 4/23/0410Walker,Harel
12
ITLC approval to proceed
100%Mon 4/26/04Mon 4/26/0411ITLC
13
UCFY / YBO
9%Tue 4/27/04Mon 7/26/0412 
14
Configure Shibboleth Apache module
100%Tue 4/27/04Mon 5/10/04 Kini
15
Implement Shib/Apache instance of JAAS
0%Tue 5/11/04Mon 6/7/0414Kini
16
Integrate JAAS into UCFY
0%Tue 4/27/04Mon 6/7/04 Barman
17
Initial integration testing
0%Tue 6/8/04Mon 6/14/0415,16Kini,Barman
18
Integration testing w/ campuses
0%Tue 6/15/04Mon 7/19/0417Kini,Barman
19
Develop user documentation
0%Tue 6/15/04Mon 7/5/0417Barman
20
Train support personnel
0%Tue 7/6/04Mon 7/12/0419Barman
21
Move to production environment
0%Tue 7/20/04Mon 7/26/0432,45Barman
22
CDL-licensed resources
0%Tue 4/27/04Tue 4/27/0412 
23
TBD
0%Tue 4/27/04Tue 4/27/04  
24
Policy
0%Tue 4/27/04Tue 4/27/0412 
25
TBD
0%Tue 4/27/04Tue 4/27/04  
26
UCSD
5%Tue 4/27/04Mon 8/2/0412 
27
Install core Shibboleth Origin
100%Tue 4/27/04Tue 4/27/04 Lawrence
28
Wrap Shibboleth w/ UCSD authN
100%Wed 4/28/04Wed 4/28/0427Lawrence
29
Bridge Shib attribute service to UCSD
100%Thu 4/29/04Thu 4/29/0428Lawrence
30
Join InCommon and InQueue
0%Fri 4/30/04Thu 5/6/0429Lawrence
31
Config Shib for InCommon/InQueue
0%Fri 5/7/04Thu 5/13/0430Lawrence
32
Integration testing
0%Tue 6/15/04Mon 7/12/0431,17Lawrence
33
Move origin to production environment
0%Tue 7/13/04Mon 7/19/0432Lawrence
34
Develop training materials
0%Tue 6/22/04Mon 7/19/0432FF+1 wkLawrence
35
Config Blink for Shibb'ed UCFY/YBO
0%Tue 7/27/04Mon 8/2/0433,34,13Lawrence
36
UCI
11%Mon 4/26/04Mon 8/2/0412 
37
Install dedicated server to host Shibboleth Origin
100%Tue 4/27/04Tue 4/27/04 Roode,Arseniev
38
Install Apache, Tomcat Java server, Sun J2SE JDK, etc.
100%Wed 4/28/04Wed 4/28/0437Roode,Arseniev
39
Install Shibboleth v1.1
100%Thu 4/29/04Thu 4/29/0438Roode,Arseniev
40
Obtain web server certificate from HEPKI
100%Fri 4/30/04Fri 4/30/0439Roode,Arseniev
41
Join the InQueue federation
100%Mon 5/3/04Mon 5/3/0440Roode,Arseniev
42
Configure Shibboleth Origin
100%Tue 5/4/04Mon 5/10/0441Roode,Arseniev
43
Set up OpenLDAP database using eduPerson schema
0%Tue 5/11/04Mon 6/14/0442Roode,Arseniev
44
Test with InQueue
0%Tue 6/15/04Mon 6/21/0443Roode,Arseniev
45
Integration testing
0%Tue 6/22/04Mon 7/19/0444,17Roode,Arseniev
46
Move to production environment
0%Tue 7/20/04Mon 7/26/0445Roode,Arseniev
47
Develop training materials
0%Tue 6/29/04Mon 7/26/0445FF+1 wkRoode,Arseniev
48
Create Shibbolized links to YCFY/YBO from UCI SNAP Portal
0%Tue 7/27/04Mon 8/2/0446,47,13Roode,Arseniev
49
Join the InCommon federation when ready
0%Mon 4/26/04Mon 4/26/04 Roode,Arseniev
50
UCLA
2%Mon 4/26/04Mon 8/2/0412 
51
Install Test Shibboleth Origin in the Technology Sandbox.
100%Tue 4/27/04Tue 4/27/04 Mahabalagiri
52
Modify Shibboleth Handle Service to work with ISIS.
100%Wed 4/28/04Wed 4/28/04 Mahabalagiri
53
Create a prototype directory to provide data service to Shibboleth Attribute Authority.
0%Tue 4/27/04Mon 5/17/04 Ma
54
Upgrade test Shibboleth Origin to pilot-worthy status.
0%Wed 4/28/04Tue 5/18/0451Mahabalagiri
55
Modify the prototype directory to match UC Federated Identity Management Requirements.
0%Tue 5/18/04Mon 6/7/0453Ma
56
Upgrade prototype directory to pilot-worthy status.
0%Tue 5/18/04Mon 6/7/0453Ma
57
Test pilot Shibboleth Origin with YBO and JSTOR.
0%Tue 6/15/04Mon 7/12/0454,56,17Mahabalagiri,Ma
58
Develop user education materials.
0%Tue 6/22/04Mon 7/19/0457FF+1 wkMahabalagiri,Ma
59
Develop support documentation / Train support staff.
0%Tue 6/22/04Mon 7/19/0457FF+1 wkMahabalagiri,Ma
60
Rollout the pilot.
0%Tue 7/27/04Mon 8/2/0457,58,59,13Mahabalagiri,Ma,Wu
61
Join InCommon.
0%Mon 4/26/04Mon 4/26/04 Wu,Worth
62
Completion Goal
0%Mon 8/2/04Mon 8/2/0426,36,50,24,13,22