UC Federated Authentication


Project Start Date: Mon 2/2/04
Project Finish Date: Mon 8/2/04

Groupware Phase I

ID
Description
% CompleteStartFinishPredecessorsPeople
1
Project Start
100%Mon 2/2/04Mon 2/2/04  
2
Identify group members
100%Mon 2/2/04Tue 2/10/041Walker,Harel
3
First group meeting
100%Mon 3/8/04Mon 3/8/042All
4
Distribute meeting notes
100%Tue 3/9/04Wed 3/17/043Walker
5
Schedule conference call
100%Thu 3/18/04Fri 3/26/044Walker
6
Conference call #1
100%Thu 4/8/04Thu 4/8/045All
7
Distribute plan to ITLC
0%Thu 4/8/04Wed 4/14/046Walker,Harel
8
Sub-project plans to DW
0%Thu 4/8/04Tue 4/13/046All
9
Draft project schedule
0%Thu 4/8/04Wed 4/14/046Walker,Harel
10
Conference call - review schedule
0%Wed 4/21/04Wed 4/21/049,8All
11
Distribute schedule to ITLC
0%Thu 4/22/04Fri 4/23/0410Walker,Harel
12
ITLC approval to proceed
0%Mon 4/26/04Mon 4/26/0411ITLC
13
UCFY / YBO
0%Tue 4/27/04Mon 7/26/0412 
14
Configure Shibboleth Apache module
0%Tue 4/27/04Mon 5/10/04 Kini
15
Implement Shib/Apache instance of JAAS
0%Tue 5/11/04Mon 6/7/0414Kini
16
Integrate JAAS into UCFY
0%Tue 4/27/04Mon 6/7/04 Barman
17
Initial integration testing
0%Tue 6/8/04Mon 6/14/0415,16Kini,Barman
18
Develop user documentation
0%Tue 6/15/04Mon 7/5/0417Barman
19
Train support personnel
0%Tue 7/6/04Mon 7/12/0418Barman
20
Move to production environment
0%Tue 7/20/04Mon 7/26/0431,44Barman
21
CDL-licensed resources
0%Tue 4/27/04Tue 4/27/0412 
22
TBD
0%Tue 4/27/04Tue 4/27/04  
23
Policy
0%Tue 4/27/04Tue 4/27/0412 
24
TBD
0%Tue 4/27/04Tue 4/27/04  
25
UCSD
5%Tue 4/27/04Mon 8/2/0412 
26
Install core Shibboleth Origin
100%Tue 4/27/04Tue 4/27/04 Lawrence
27
Wrap Shibboleth w/ UCSD authN
100%Wed 4/28/04Wed 4/28/0426Lawrence
28
Bridge Shib attribute service to UCSD
100%Thu 4/29/04Thu 4/29/0427Lawrence
29
Join InCommon and InQueue
0%Fri 4/30/04Thu 5/6/0428Lawrence
30
Config Shib for InCommon/InQueue
0%Fri 5/7/04Thu 5/13/0429Lawrence
31
Integration testing
0%Tue 6/15/04Mon 7/12/0430,17Lawrence
32
Move origin to production environment
0%Tue 7/13/04Mon 7/19/0431Lawrence
33
Develop training materials
0%Tue 6/22/04Mon 7/19/0431FF+1 wkLawrence
34
Config Blink for Shibb'ed UCFY/YBO
0%Tue 7/27/04Mon 8/2/0432,33,13Lawrence
35
UCI
6%Mon 4/26/04Mon 8/2/0412 
36
Install dedicated server to host Shibboleth Origin
100%Tue 4/27/04Tue 4/27/04 Roode,Arseniev
37
Install Apache, Tomcat Java server, Sun J2SE JDK, etc.
100%Wed 4/28/04Wed 4/28/0436Roode,Arseniev
38
Install Shibboleth v1.1
100%Thu 4/29/04Thu 4/29/0437Roode,Arseniev
39
Obtain web server certificate from HEPKI
100%Fri 4/30/04Fri 4/30/0438Roode,Arseniev
40
Join the InQueue federation
100%Mon 5/3/04Mon 5/3/0439Roode,Arseniev
41
Configure Shibboleth Origin
0%Tue 5/4/04Mon 5/10/0440Roode,Arseniev
42
Set up OpenLDAP database using eduPerson schema
0%Tue 5/11/04Mon 6/14/0441Roode,Arseniev
43
Test with InQueue
0%Tue 6/15/04Mon 6/21/0442Roode,Arseniev
44
Integration testing
0%Tue 6/22/04Mon 7/19/0443,17Roode,Arseniev
45
Move to production environment
0%Tue 7/20/04Mon 7/26/0444Roode,Arseniev
46
Develop training materials
0%Tue 6/29/04Mon 7/26/0444FF+1 wkRoode,Arseniev
47
Create Shibbolized links to YCFY/YBO from UCI SNAP Portal
0%Tue 7/27/04Mon 8/2/0445,46,13Roode,Arseniev
48
Join the InCommon federation when ready
0%Mon 4/26/04Mon 4/26/04 Roode,Arseniev
49
UCLA
0%Tue 4/27/04Tue 4/27/0412 
50
TBD
0%Tue 4/27/04Tue 4/27/04  
51
Completion Goal
0%Mon 8/2/04Mon 8/2/0425,35,49,23,13,21