RD1.7 RESPONSIBILITIES OF THE INSPECTOR
(see [II]:2.2)
The inspector, whether employed by the design professional or the University, shall:
- Become thoroughly familiar with contract document requirements, applicable codes and standards, approved
submittals, and all instructions or clarifications issued by the design professional.
- Generally act as liaison between the contractor and the design professional.
- Keep a log of written communications including submittals received from or issued to the contractor.
- As appropriate to the nature and extent of construction, monitor the quality and quantity of the work and promptly report
to the design professional nonconforming work or nonconforming work performance.
- Prepare a daily report recording:
- Inspector's time and activities on the project.
- Weather conditions.
- Nature and location of work being performed and by whom.
- Number of workers by trade.
- Oral instructions and interpretations given by the design professional.
- Specific observations on results of oral instructions and interpretations.
- Any occurrence or work which might result in a claim for a change in the contract sum or contract time.
- Names of visitors, their titles, and the time and purpose of their visit.
- This report shall be prepared for each normal work day or for each day on which the contractor performs work, and
a copy shall be promptly sent to the design professional and the University.
- Observe testing and inspection done by the contractor as required in the contract documents and coordinate and
observe special testing and inspection when requested by the design professional or University.
- Monitor the contractor's proposed schedule and the actual construction schedule and promptly report to the design
professional discrepancies between the schedules and any conditions which may cause construction delays.
- Periodically photograph the work, paying special attention to portions of the work that have been or may be rejected
or may be associated with a claim or delay.
- Review in detail the contractor's Application for Payment and report the findings of this review to the design
professional.
The inspector shall not:
- Authorize deviations from the contract documents.
- Approve substitute materials or equipment.
- Advise on or issue directions concerning aspects of construction means, methods, techniques, sequences, or
procedures in connection with the work.
Back to Table of Contents