CHAPTER 3
PREPARING TO SOLICIT BIDS
Before bids can be solicited, basic conditions required by University policies, delegations of authority, and federal and state regulations must be met. These conditions apply to competitive and informal bidding and negotiated contracting. (See Permission to Solicit Bids, RD2.42.)
References:
- California Code of Regulations, Title 24, California Building Standards Code.
- Permission to Solicit Bids (see RD2.42).
- UC CEQA Handbook, Procedural Handbook and Model Approach for Implementing the California Environmental Quality Act (CEQA), University of California, Office of Long-Range Planning, Office of the President, Oakland, CA, May 1991, revised February 1994.
- University policy: "Equal Opportunity in University Business Contracting" [Interim Policy] (see FM1:5.1).
- University policy: "Nondiscrimination on the Basis of Handicap" (see FM1:5.1).
- University policy: "Seismic Safety" (see FM1:5.1).
Before soliciting bids for any construction contract, the University's Designated Administrator must ensure that all of the following conditions are met:
(See FM3[I]:4 for more information on code compliance in regard to project design and construction.)
Before bids are solicited, the University accounting officer must certify that project funds are available in the plant account approved for the project. Signature for certification of fund availability is included on the Pre-Bid Capital Improvement Budget. The source and amount of funds must match the most recently approved Capital Improvement Budget (CIB) for the project. The approval authority for CIBs depends on the fund source and size of the project. Contact the Office of the President to determine authority.
For state-funded projects, funds are frequently transferred from the state to the University in increments. For such projects, formal action by the State Department of Finance to "release" funds to the University and authorize proceeding with work is sufficient basis for signifying availability of funds.
3.2.2 Non-State-Funded Projects
Most non-state-funded projects must have funds physically transferred into the plant account to proceed with solicitation of bids. Exceptions are discussed below.
For externally financed projects, the Treasurer's Office must notify the Facility that funds are available. Regents' approval of external financing is not sufficient, as it does not mean that funds are immediately available.
Gift pledges (not yet-in-hand) are not an appropriate source of funds for the purposes of bid solicitation. Prior to solicitation of bids for a project with outstanding pledges, the following must occur: (1) The Regents have approved authorization for a standby loan and the Treasurer's Office has notified the Facility that funds are available, or (2) a cash advance from another lawfully available source is temporarily transferred into the plant account and reimbursed as gifts are received.
Some federally-funded projects require that bidding documents be reviewed by the appropriate federal agency for permission to advertise for bid. Refer to the agency agreement for the specific requirements.
Capital projects funded by State capital appropriations require the submittal to, and approval by, the State Department of Finance (DOF) or State Public Works Board (SPWB) (if the project is funded with lease-revenue bonds) of the final, 100% complete bid documents package with all signatures and approvals by the designated Campus Fire Marshall or Division of the State Architect/Access Compliance. The project as detailed by the documents must be within approved scope, budget and schedule. The Facility submits the completed bid document package, including drawings and specifications, with supporting documentation that includes explanatory cover letter, project description, project Capital Improvement budget, detailed cost estimate, component cost summary, area reconciliation, project schedule, and record of final EIR action (if pertinent) to the Office of the President for review and processing. Any bid alternates must be explicitly identified; alternates may not be bid legally without specific state approval of the individual alternates. The documents are transmitted to the DOF, with copies as required to other State agencies, for review and approval and release of the construction funds. The project may be put out to bid upon the release of construction funds. If the lowest responsive and responsible bid is within budget, the construction contract may be awarded. Contact the Office of the President for more detailed and updated information regarding submittal documentation and process or for clarification as necessary.
3.3.2 Lease-Revenue Bond-Funded Projects
Capital construction and capital equipment purchases for projects funded with State lease-revenue bonds (in which the State owns the facility and leases it to the University) require steps in addition to those outlined in 3.3.1 above. Prior to obtaining approval of the bid document package submittal, a proposed site lease, facility lease, and equipment lease (if applicable), and Regents authorization must be submitted to the SPWB for approval. These documents must be in place and approved by the SPWB prior to bid. In order to accomplish this, the Facility must first prepare and transmit to the Office of the President a legal description and site survey, and submit a Regents item requesting authorization to prepare and execute the leases and agreements.
Upon approval by The Regents, the Office of the President request General Counsel to prepare the legal documents. The Office of the President coordinates and submits the necessary documents, in parallel with the bid document package submittal, to SPWB for review and action. The bid document package for a lease-revenue bond-funded project must be approved by the SPWB, rather than DOF. Upon approval by the SPWB of the bid document package, the leases and agreements, and arrangements for interim financing, the University will be authorized to proceed to solicit bids. At conclusion of the bidding phase, the Facility reports the bid results and apparent low responsible bidder to the Office of the President for transmittal to the DOF with a request for approval and authorization to award the contract (see[I]:8.2.1). Upon receipt of this authorization and interim financing, the contract can be awarded and work can proceed.
The bid document package as submitted to, and approved by the State, must be the same as the bidding documents issued and must become part of the Facility's project file [see RD1.3, Project File Contents, FM3[I]:6, and [II]:1.1.3).
On projects funded in whole or in part by the federal government, the rules of the funding agency must be reviewed for competitive bidding and public advertising requirements. Normally, federal agencies require competitive bidding with public advertising only on projects with estimated construction costs exceeding $10,000. If federal requirements are more restritive than University policy, the more restrictive requirements must be followed.
If the funding agency requires an affirmative action program as a condition for funding, then an affirmative action program that is in compliance with the funding agency's requirements must be included in the bidding documents and the contract documents.
3.5.1 American Recovery and Reinvestment Act of 2009
(ARRA)
If the project is funded in whole or in part through the
American Recovery and Reinvestment Act of 2009 (ARRA), see following guidelines
for compliance:
For all grant-funded construction projects, whether new construction,
renovation, maintenance, repair or upgrade, the terms of the grant may add
compliance requirements different from those of the University's "typical"
project. Federal grants funded as
part of ARRA (the American Recovery and Reinvestment Act of 2009) entail a
separate set of compliance requirements, some of which vary depending on the
funding agency (NIH, DOE, NSF, etc.).
While many ARRA-funded University projects have now been completed,
some are still in process and others have not yet gone out to bid. The purpose of these guidelines is to
suggest those requirements of ARRA that might otherwise be overlooked so that
University staff can determine their applicability to specific projects, obtain
more detailed guidance and comply fully with all
requirements.
All requirements flow down from the grant recipient to its
contractors and subcontractors (collectively "vendors") who receive more than
$25,000 in ARRA funds. Longer
record retention may be required.
Highlights of key requirements of ARRA include (not an exhaustive
list):
Reporting
Quarterly reporting of specific data elements is required on the use
of all funds received, including the number of jobs created and/or
saved.
CCR Registration
The University and its vendors (its contractors and subcontractors)
must all register in the CCR (Central Contractor Registration) database at
www.ccr.gov . Each entity needs a
DUNS number to register.
Buy American
Unless an exemption applies, the project must use American iron,
steel and manufactured goods.
Davis-Bacon Wage Rates
The Davis-Bacon Act requires that workers not be paid less than the
applicable wage determination, which may be found at http://www.wdol.gov/
. (If California prevailing wage is higher, the higher wage must
be paid.) Certified payrolls must
be checked for compliance and records must be retained as required. (LCPtracker
http://www.lcptracker.com/ or similar software can be
helpful.)
Segregated Accounting
ARRA funds must be tracked, accounted for and reported separately
from all other project funds.
Waste, Fraud and Abuse
The University and its vendors have an affirmative duty to report
false claims and other misconduct.
Whistleblower Protection
The protection extends to employees of the University and its
vendors.
Public Information
Information about the use of funds will be posted at www.recovery.gov based on submitted reports.
Information about ARRA requirements must be included in
advertisements for bids, bid packages and contract documents. Specific information must be posted at
the job site. Failure to comply
with the requirements can result in loss of
funds.
The laws and regulations encompassed by ARRA are complex. Specific guidance should be obtained from the campus sponsored projects or contracts and grants office, in consultation with the principal investigator of the project and the contract and grants officer with whom he or she has been working.
Go to Next
Chapter
Revised May 2, 2011 (Revision # FM 11-013-G)